Consultar ensayos de calidad


Material handling in mining – los pelambres



MATERIAL HANDLING IN MINING – LOS PELAMBRES

When by the end of 1999 the Los Pelambres overland conveyor system starts its operation, a new benchmark in belt conveyor technology will be set. This presentation gives an introduction into the design of this record breaking conveyor system and will elaborate on some of its innovative features.

Introduction The Los Pelambres copper mine is located approximately 200 km north of Santiago, Chile, high in the Andean mountains next to the border to Argentina. When the owner decided to proceed with a major expansion, it became necessary to find an efficient way to transport the coarse ore from the mine to the new concentrator facility at a rate of 8,700 metric tons per hour, over a distance of some 13 kilometers and dropping over 1300 meters in elevation. To handle this task, a belt conveyor system consisting of three individual conveyors has been selected. To protect the conveyor from the rock slides and avalanches prevalent in this area, most of the conveyor runs inside tunnels which have been driven through the mountain side.



Conveyor Layout

In July of 1997, a contract was awarded to Krupp Canada to design and supply the entire coarse ore conveyor system. At the time of this presentation, the installation of the conveyor system is nearing completion. The commissioning of the system is expected to take place in the last quarter of 1999. Conveyor Layout Copper ore is transported by large mine haultrucks to the primary crushing plant located at the outside perimeter of the mine. A gyratory crusher reduces the run-of-mine material to belt-conveyor acceptable particle sizes of 300 mm and less. The crushed material is collected in a surge bin underneath the crusher, then reclaimed by the crusher discharge conveyor and stacked onto the

Crusher Discharge Conveyor and Mine Stockpile


Material Handling in Mining – A Case Study

Technical Seminar 1999

mine ore stockpile. With a belt width of 3,000 mm at a belt speed of 3 meters per second, the crusher discharge conveyor is designed to convey 14,000 tons per hour. The material is reclaimed from the mine stockpile by four belt feeders and loaded onto the first of the three coarse ore overland conveyors. At the end of the coarse ore conveyor system, the copper ore is discharged onto the concentrator stockpile. The discharge end of the last coarse ore overland conveyor can shuttle back and forth over a distance of 62 meters, stacking the material onto the longitudinal stockpile.

Head End Conveyor Cv-007 with Concentrator Stockpile location

The overall conveying distance of 12.7 kilometers is divided into three individual conveyors of 6.0 km (CV-005), 5.3 km (CV-006), and 1.4 km (CV-007) lengths. The conveyors follow a downhill slope of approximately 10 % with a short 25% slope at the end of the tunnel at conveyor CV-007. Drive System Due to their similar length and vertical drop, conveyors CV-005 and CV-006 arelargely identical with regard to their drive configuration. Both conveyors are equipped each with four 2,500 kW drives. Conveyor CV-007 is equipped with two 2,500 kW drives, bringing the total installed drive power to 25 MW. The conveyor system will operate in motoric mode at low capacities, and will change to generative operation at a belt loading of 20% or more. In this condition, the drives will feed electrical energy back into the power grid. The electric motors are regulated by adjustable frequency drives (AFD). When started, the conveyors are accelerated in 40 seconds following a S-shaped speed curve. Stopping is performed in Drive Station Conveyor CV-005 sequence based on predetermined stopping ramps ranging in length from 76 to 80 seconds. Operational parameters, such as belt speed, belt tension, belt loading, motor torque, etc. are continuously monitored and processed by the drive control system to adjust the speed and to detect any possible failure. Since loss of control can lead to catastrophic consequences for a downhill conveyor of this magnitude, utmost attention was given to the control system. Depending on the diagnosed conditions, the conveyor system can be brought to a complete stop in several different ways: In fully functional conditions, the drives will be decelerated by the AFD to their full stop, by feeding the electric energy into the power network. In case of power failure (network not available), the electric energy is diverted into externalresistors, allowing stopping the conveyors electrically without external power. As a next level of safety, a large mechanical brake system is installed, consisting of a total of 13 disc brakes, with a diameter of 2500 mm each. The mechanical brake system can either operate fully PLC controlled, following a determined deceleration ramp, or in case of PLC failure or hydraulic failure, engage mechanically (fail safe).

2


Material Handling in Mining – A Case Study

Technical Seminar 1999

Great effort was made to develop a suitable mechanical brake system. The temperatures generated by the mechanical brakes during an emergency stop create a challenge regarding the selection of the brake lining material and the brake disc Conveyor Belt ST-7800 design. Also, in the interest of safety, almost all brake control components are fully redundant. Conveyor Belt

Brake Caliper Assembly

Conveyors CV-005 and CV-006 are equipped with steel cable belting rated at ST-7800. This marks a new world record for conveyor belting, assuming the distinctions of the world’s strongest conveyor belt from the Prosper-Haniel mine in Germany, which carried the record for the last 14 years. Belt forces will reach 250 tons during running, and can peak at 320 tons during emergency braking. Special attention was given to the splice as the weakest link of the belt. Testing performed at the University of Hanover, Germany showed that the fatigue strength of the splice exceeds 50% of the ultimate brakingstrength of the belt. As a safeguard, a splice failure detection system has been provided for the first time. This system is designed to detect splice elongation resulting from impending splice failure, and to safely stop the conveyor before the damage occurs. Reducers The 2500 kW two-stage helical bevel reducers are the largest reducers ever employed for conveyor drives. At a unit weight of 26 tons, the reducers are fully self-cooling and do not rely on auxiliary devices for temperature regulation. Several studies were made by Universities and scientific institutes to validate the reducer design, such as a heat dissipation study, a finite element analysis of the housing, and a bearing smear study.
2500 kW Conveyor Drive Reducers during Testing

3


Material Handling in Mining – A Case Study

Technical Seminar 1999

Pulleys As another new record, the drive pulleys supplied for the Los Pelambres overland conveyors are the largest conveyor pulleys built to date. The pulleys have a shell diameter of 2,500 mm. The pulley shaft measures 630 mm in diameter. The bearings have an inside diameter of 560 mm. The total assembly weight is 37 tons per pulley. Conclusion The Los Pelambres overland conveyor system sets a new standard for many aspects of belt conveyor design. While it is technically possible to build yet larger systems, it can be assumed that the limits of practicality and economy will not allow pushing the envelope much further.

Conveyor Drive Pulley

4


Política de privacidad